Net Billing Explained — Pakistan's February 2026 Solar Rules
Net metering is over for new connections. Here is what replaced it, in plain words.
On 9 February 2026, NEPRA's Prosumer Regulations (S.R.O. 251(I)/2026) replaced net metering with net billing for all new rooftop solar connections. The change is one number that matters: what the grid pays you for the electricity you send back.
Not a government website. This page explains the rules as notified; your DISCO's net-billing agreement is the authority for your connection.
| Old net metering (pre-Feb 2026 agreements) | Exported units credited at about Rs 25.32/unit — well below the top retail slabs |
| Net billing (new connections) | Exported units bought at Rs 8.13/unit (rate for Apr–Jun 2026, NEPRA S.R.O. 1501(I)/2026); you still pay the full retail tariff on every unit you import |
| Agreement length | 5 years (was 7 under net metering), renewable by mutual consent; NEPRA can revise the export rate during the term |
| Size limit | Up to your sanctioned load, maximum 1 MW; no new connection if the local transformer is already 80% loaded |
| Source | NEPRA (Prosumer) Regulations 2026, S.R.O. 251(I)/2026 — checked 27 November 2026 |
What this means for a home buying solar today
- Self-used solar is still very valuable. Every unit your home uses directly is a unit you do not buy at Rs 22–47. That saving did not change.
- Exported solar is worth much less. At Rs 8.13/unit, a system sized far beyond your daytime use pays back slowly. Size to your daytime load — the solar estimator does exactly this maths.
- Batteries make more sense than before. Storing your own solar for the evening beats selling it at Rs 8.13 and buying it back at night rates.
- Old net metering is protected — do not give it up carelessly. If your agreement predates 9 February 2026, you keep your terms. But modifying your system (for example increasing its size) can be treated as a new connection and move you onto net billing. Check with your DISCO before changing anything.
Checker: am I protected on the old net metering?
Answer both questions to see your position.
How to apply for a net billing connection
- Check your sanctioned load and phase. Your system cannot exceed your sanctioned load; most DISCOs require a three-phase connection for larger systems.
- Install with an AEDB-certified installer using approved inverter and protection equipment — uncertified installs are the commonest reason applications stall.
- Apply through your DISCO (for PITC companies, the application starts on the DISCO's net-metering portal; K-Electric has its own process). Documents usually asked: CNIC, latest paid bill, system documents and inverter certificates.
- Inspection and agreement. The DISCO inspects, a bi-directional meter is installed, and you sign the 5-year net billing agreement.
- Read your first bill carefully. Imported and exported units are shown separately; exports are credited at the notified rate (Rs 8.13/unit for Apr–Jun 2026).
Timelines vary widely by DISCO — the full process commonly takes 30–90 days. Homes up to 25 kW were reported exempt from the NEPRA concurrence fee from April 2026; confirm the current fee position with your DISCO when you apply, as this detail has changed more than once.